Reconstruction and modernization of pumping stations - Zhekov vir
Investor: Asarel-Medet AD
Contractor: Vodstroy Plovdiv AD
Role of ENGINEERING EAD: Subcontractor - electrical part
Location: Panagyurishte town, Bulgaria
Contract value: BGN 315 767.47 without VAT
Reconstruction and modernization of pumping stations of the water supply system "Zhekov vir", located on the territory of "Asarel-Medet" AD in parts Electrical, Instrumentation and automation. Retrofit and equipment of 6 and 20kV output cells in a substation. Complete retrofit and commissioning of 6 and 20 kV switchgear. Construction of air cable transitions. Construction of district lighting. Construction of MV and LV cable lines. Construction and adjustment of SCADA system.