Installation of cable accessories 110kV on cable line to "MONDI" paper producer (stage 1)

Investor: Mondi Stamboliyski EAD
Contractor: Electriccity Ltd
Role of FILKAB AD / ENGINEERING EAD: Subcontractors
Location: Stamboliyski, Bulgaria
Contract value: BGN 250,000. without VAT
Year of implementation: 2012

The activities of the project include the construction of a 110KV cable line from the 110/6.3kV substation located on the territory of the "MONDI" in the town of Stamboliyski to the 110/20/6kV "Novi Krichim" substation.

1980 meters of cable 2XS(FL)2Y 64/110kV 1x300rm/95 manufactured by TFkable Poland, as well as the necessary cable glands and outdoor cable terminations 110kV manufactured by Pfisterer Switzerland were delivered and installed. The delivery of the components for the construction of the cable line was carried out by FILKAB AD. The company fully undertakes the project management activities, provides supervision of the laying of the HV cable and the installation of the relevant cable accessories.

The installation of the 110kV cable accessories was carried out by ENGINEERING EAD, the company has trained and certified personnel for this.